A trench is a long box: length × width × depth gives cubic feet, and dividing by 27 gives cubic yards, the unit trucks and suppliers use. Backfill is the trench volume minus the space the pipe now takes up.

On the job

Ordering haul-off trucks, bedding sand and backfill for a main replacement all come from these numbers.

On the exam conversion sheet

The sheet lists 1 yd³ = 27 Ft³ and 1 yd = 3 Ft. Change any width in inches to feet before you multiply.

What the exam can ask

These are the 3 kinds of trench volume problem the Pass My Certs app practices for the D2 exam. Each opens a fresh problem with new numbers.

Worked examples

Worked example 1

Trench volume with the width in inches

A trench for a new main is 220 feet long, 42 inches wide, and 4.5 feet deep. How many cubic yards of soil are dug out?

  1. Change the width from inches to feet. Divide by 12.42 in ÷ 12 = 3.5 ft
  2. Find the volume in cubic feet. Volume = Length × Width × Depth.220 ft × 3.5 ft × 4.5 ft = 3,465 cu ft
  3. Change cubic feet to cubic yards. Divide by 27.3,465 cu ft ÷ 27 cu ft/cu yd = 128.333 cu yd
  4. Round only at the very end. The steps above kept every digit, even though they show shorter numbers.128.333... rounds to 128 cubic yards

Answer 128 cubic yards

The wrong answers on the multiple choice version, and how people get them
  • 385 cubic yards: You divided by 9. That is the number of square feet in a square yard. A cubic yard has 27 cubic feet (3 × 3 × 3).
  • 3,465 cubic yards: This is cubic feet. Divide by 27 to get cubic yards.
  • 1,540 cubic yards: You left the width in inches. Change it to feet first (÷ 12).

Try one like this with new numbers in the app. No account needed.

Worked example 2

Backfill needed after the pipe is laid

A trench is 930 feet long, 2.5 feet wide, and 5 feet deep. After an 8-inch main is laid in it, how many cubic yards of backfill are needed to fill the trench?

  1. Find the trench volume. Volume = Length × Width × Depth.930 ft × 2.5 ft × 5 ft = 11,625 cu ft
  2. Change the pipe diameter from inches to feet. Divide by 12.8 in ÷ 12 in/ft = 0.6667 ft
  3. Find the area of the circle (outside of the pipe). Area = 0.785 × D × D.0.785 × 0.6667 ft × 0.6667 ft = 0.3489 sq ft
  4. Find the space the pipe takes up. Volume = Area × Length.0.3489 sq ft × 930 ft = 324.467 cu ft
  5. Subtract the pipe from the trench.11,625 cu ft − 324.467 cu ft = 11,300.5 cu ft
  6. Change cubic feet to cubic yards. Divide by 27.11,300.5 cu ft ÷ 27 cu ft/cu yd = 418.538 cu yd
  7. Round only at the very end. The steps above kept every digit, even though they show shorter numbers.418.538... rounds to 419 cubic yards

Answer 419 cubic yards

The wrong answers on the multiple choice version, and how people get them
  • 1,256 cubic yards: You divided by 9. That is the number of square feet in a square yard. A cubic yard has 27 cubic feet (3 × 3 × 3).
  • 11,301 cubic yards: This is cubic feet. Divide by 27 to get cubic yards.
  • 443 cubic yards: You added the pipe volume. The pipe takes up space, so subtract it.

Try one like this with new numbers in the app. No account needed.

Where people lose points

  • Multiplying a width in inches with lengths in feet.
  • Dividing by 9 instead of 27. Nine is for square yards, 27 is for cubic yards.
  • Forgetting to subtract the pipe volume for backfill.